15 MW Electrolysis Pilot Plant RWE
RWE initiated a groundbreaking 15 MW electrolysis pilot project to research large-scale hydrogen production for the integration of renewable energies. Artelia played a central role by preparing the design plans and the necessary application documents in accordance with the Federal Emission Control Act.
Maintaining confidentiality between the electrolyser manufacturers was a particular challenge that required precise coordination. Artelia’s competent management successfully mastered this demanding task, enabling smooth cooperation. After a short planning period of four months, the approval notice was issued just 1.5 months after the documents were submitted.
Maintaining confidentiality between the electrolyser manufacturers was a particular challenge that required precise coordination. Artelia’s competent management successfully mastered this demanding task, enabling smooth cooperation. After a short planning period of four months, the approval notice was issued just 1.5 months after the documents were submitted.
- Germany, Lingen
- RWE Technologie International
- 2021 - 2022
-
Feasibility Design
LPH 1-4 HOAI
Coordination of external experts and engineering firms
Permitting management in accordance with BImSchG
Implementation of confidentiality protocols between electrolyser
OEMs